Steel Structures

Food plant production hall & mezzanine, Buraidah

Client
Tamween Food Industries
Location
Buraidah
Year
2022
Duration
14 weeks
Steel erected
172 t
Mezzanine area
640 m²
CASE STUDY

172 t of hall steel and a 640 m² process mezzanine handed over in 14 weeks.

The challenge

A food-processing hall in Buraidah needed frame, mezzanine and racking posts on a fixed opening date, with a hygiene spec that banned on-site welding once the envelope was sealed. Base plates also had to clear embedded services the client’s engineer added late in the design.

Our approach

Everything was fabricated and match-marked in Madinah — including the mezzanine and all racking and shelving posts — so site work was lifting and bolting only. Embedded services were re-surveyed before steel arrived and two base plates were relocated in the workshop, not on site. Erection ran with two crews of eleven behind an 80-tonne crane, and the frame was bolted, braced and released to the cladding crew in six weeks.

The result

Handover in 14 weeks: 172 tonnes, 640 m² mezzanine and 48 racking posts installed, zero welds made inside the sealed envelope, zero lost-time injuries across 18,600 safe man-hours.

Scope delivered

  • Fabrication & match-marking in Madinah
  • Base plates set around embedded services
  • Hall frame erected behind an 80-t crane
  • Process mezzanine bolted in place
  • Racking & shelving posts installed
  • No-weld handover to the cladding crew
Related service: Steel Structures
SAFETY ON THIS PROJECT
0Lost-time injuries
18,600Safe man-hours
26Crew on site at peak
84Toolbox talks held
Zero welding inside a sealed food hall was written into our hygiene plan — they never once needed a grinder on site.
Engineering lead · Tamween Food Industries