Civil Works & Roads

Distribution yard road rehabilitation, Jeddah

Client
Barakah Distribution
Location
Jeddah
Year
2022
Duration
8 weeks
Roads resurfaced
1.9 km
Night slices
11
CASE STUDY

1.9 km of yard roads resurfaced in eight weeks, all gate lanes open every morning.

The challenge

Wheel-tracking had rutted the main haul routes of a busy Jeddah distribution yard, and the client could not close any gate lane — 400 trucks a day entered across three gates. Millings and new asphalt had to be laid in slices that left a live lane at every gate by 06:00.

Our approach

The work was cut into eleven night slices, each milled, paved and compacted between 21:00 and 05:30 with tie-in mats at both ends so trucks could cross at dawn. Kerb and gully adjustments were done in the same night closure, joints were cut and sealed before opening, and a rolling coordinator held a 05:00 call with the yard controller to confirm each slice’s readiness.

The result

Eight weeks, 1.9 km resurfaced with zero morning lane closures, zero delivery delays logged, zero lost-time injuries across 9,300 safe man-hours — and ride quality measured better than the original build on the first re-survey.

Scope delivered

  • Condition survey & rut-depth mapping
  • Eleven night milling-and-paving slices
  • Tie-in mats keeping three gates live at dawn
  • Kerb & gully adjustments in night closures
  • Joint cutting & sealing before each opening
  • Ride-quality verification survey
Related service: Civil Works & Roads
SAFETY ON THIS PROJECT
0Lost-time injuries
9,300Safe man-hours
14Crew on site at peak
48Toolbox talks held
Eleven nights, four hundred trucks a day, zero delays at the gates. The 05:00 call became our favourite habit.
Yard operations lead · Barakah Distribution