Steel Structures

Petrochemical maintenance workshop — steel package, Jubail Industrial City

Client
Rimal Industrial Contracting
Location
Jubail Industrial City
Year
2024
Duration
12 weeks
Steel fabricated
148 t
Workshop area
4,200 m²
CASE STUDY

148 t of built-up sections fabricated and erected in 12 weeks with 100% NDT acceptance.

The challenge

A 4,200 m² maintenance workshop was needed beside a live petrochemical complex. Deliveries could only use the shared gate between 22:00 and 05:00, third-party inspection was written into the specification, and the client’s tolerance for weld defects was zero.

Our approach

Plate girders and columns were jig-fitted and welded in our Madinah workshop by qualified welders to the approved procedure, with ultrasonic testing on 10% of full-penetration welds and mill certificates traced member by member. Loads were bundled in erection sequence and delivered through the night gate; a crew of fourteen erected behind a 60-tonne crane, and secondary steel — platforms, ladders and handrails — followed the frame in the same mobilisation.

The result

Handover after 12 weeks with 148 tonnes in place, every NDT and dimensional report accepted first time, and zero lost-time injuries across 11,400 safe man-hours. Rimal added Red Ocean to their approved fabricator list for the complex.

Scope delivered

  • Cutting, jig fit-up & welding of built-up sections
  • UT testing on 100% of full-penetration welds
  • Shop primer & match-marking for erection
  • Night-gate deliveries in erection sequence
  • Erection of frame behind a 60-tonne crane
  • Platforms, ladders & handrails installed
Related service: Steel Structures
SAFETY ON THIS PROJECT
0Lost-time injuries
11,400Safe man-hours
16Crew on site at peak
72Toolbox talks held
Weld records and NDT reports were complete on the day of handover. Night deliveries never once held up our programme.
Fabrication manager · Rimal Industrial Contracting