Civil Works & Roads

Coastal estate civil works package, Jazan

Client
Jazan Coastal Development
Location
Jazan
Year
2023
Duration
14 weeks
Earthworks
42,000 m³
Estate roads
1.1 km
CASE STUDY

42,000 m³ of earthworks and the full estate infrastructure completed in 14 weeks.

The challenge

A coastal estate near Jazan port sat on a high water table with soft fill down to 3 m. Excavation for services kept taking water, summer rains arrived in short violent bursts, and the developer needed infrastructure complete before a contractor started six villas and a retail row.

Our approach

We dewatered with wellpoints along the utility corridors and swapped two foundation zones to engineered fill after CBR testing showed the natural ground would not carry loads. Earthworks ran 42,000 m³ with geotextile separation layers, storm drainage was laid first and to falls that account for Jazan’s rain intensity, and 1.1 km of estate roads followed with kerbs and full-depth shoulders. Rain days were absorbed by pulling forward drainage work in the dry corridors.

The result

Fourteen weeks: infrastructure handed over ready for building starts, all compaction and CBR tests passed, zero lost-time injuries across 19,400 safe man-hours at a peak crew of 28, and no rework was required on any settlement-sensitive service trench.

Scope delivered

  • Wellpoint dewatering along utility corridors
  • 42,000 m³ earthworks & engineered fill zones
  • Storm drainage laid first to true falls
  • Subgrade & CBR verification programme
  • 1.1 km estate roads, kerbs & shoulders
  • Geotextile separation & compaction records
Related service: Civil Works & Roads
SAFETY ON THIS PROJECT
0Lost-time injuries
19,400Safe man-hours
28Crew on site at peak
84Toolbox talks held
They dealt with our water table before it became our problem — the villa contractor started on a dry, level platform.
Estate manager · Jazan Coastal Development

Need a team that has done this before?

Request a quote