jubail-plant-shutdown-steel-tie-ins
Mechanical Works

Plant shutdown steel tie-ins, Jubail Industrial City

Client
Ghazal Petrochemicals
Location
Jubail Industrial City
Year
2025
Shutdown window
14 days
Members replaced
18
New frames
12
CASE STUDY

18 members cut out and 12 new frames installed inside a 14-day shutdown — zero day-over.

The challenge

A new pump skid needed steel modifications inside a 14-day plant shutdown. Eighteen existing members had to be cut out and twelve new frames erected while adjacent units stayed live, every hour beyond the window carried liquidated damages, and no hot work could start until line break certificates were signed.

Our approach

Every cut and frame was pre-fabricated and trial-assembled in the workshop so site work was removal, fit-up and bolting. We rehearsed the sequence in a mock-up yard, staged materials 40 m from the work face, and ran two shifts with permit-to-work, gas testing and fire watch on each. Cuts used cold methods where fire risk demanded, and survey checks ran after every frame so alignment errors never waited for the end.

The result

All tie-ins completed six hours inside the 14-day window — 18 members removed, 12 frames installed and surveyed, zero lost-time incidents across 9,700 safe man-hours at a peak crew of 28, and no extension to the shutdown was requested.

Scope delivered

  • Workshop trial assembly of all new frames
  • Line break confirmation & permit staging
  • Cold cutting of 18 existing members
  • Twelve new frames fitted & bolted
  • Survey checks after every frame
  • Two-shift execution with gas testing & fire watch
Related service: Mechanical Works
SAFETY ON THIS PROJECT
0Lost-time injuries
9,700Safe man-hours
28Crew on site at peak
40Toolbox talks held
They finished six hours early and the units restarted on the hour we planned. The mock-up yard rehearsal was the difference.
Shutdown coordinator · Ghazal Petrochemicals