Mechanical Works

Retail anchor mezzanine cutting & erection, Riyadh

Client
Mawaddah Retail Group
Location
Riyadh
Year
2024
Duration
7 weeks
Mezzanine area
1,250 m²
Night windows
49
CASE STUDY

1,250 m² mezzanine erected over a live retail anchor in seven weeks of night works.

The challenge

An anchor tenant wanted a 1,250 m² mezzanine above its sales floor with the store trading every day. Openings had to be cut into the existing frame, ceiling voids above were full of live services, and the mall prohibited impact noise during trading hours and limited loading-bay use to 01:00–05:00.

Our approach

We cut and drilled only between 01:00 and 06:00 using diamond tooling with vacuum extraction to keep dust off the stock, after mapping every ceiling service with scans. The mezzanine was erected in nine pre-assembled bays with a temporary propping sequence that kept loads off the existing columns until the frame tied in, and deck sheets were laid and noise-generating works finished before each 06:00 handback.

The result

Seven weeks of night work with zero trading-hour stoppages, zero dust complaints, and a handback checklist signed every morning. The mezzanine was load-tested and handed over three days early with zero lost-time injuries across 7,900 safe man-hours.

Scope delivered

  • Service scanning before every cut
  • Diamond cutting of frame openings at night
  • Nine pre-assembled mezzanine bays erected
  • Temporary propping & final tie-in
  • Deck sheets laid before 06:00 handback
  • Load test & handover dossier
Related service: Mechanical Works
SAFETY ON THIS PROJECT
0Lost-time injuries
7,900Safe man-hours
18Crew on site at peak
42Toolbox talks held
Forty-nine night shifts, zero trading-hour stoppages, and not one dust complaint from the store. Outstanding discipline.
Retail operations director · Mawaddah Retail Group

Need a team that has done this before?