Mechanical Works

Refinery pipe-rack modification, Yanbu

Client
Nawah Energy Services
Location
Yanbu
Year
2023
Duration
5 weeks
Members reinforced
22
Deflection limit
5 mm
CASE STUDY

22 members cut and reinforced to carry a new 20-inch line, completed in five weeks.

The challenge

A 20-inch line rerouted through an existing pipe rack required cutting out and reinforcing 22 members in a rack that carried six live services. The rack could not be taken out of service, gas tests were required before every cut, and deflection limits of 5 mm were set for the bays under modification.

Our approach

Each modification was engineered as a staged sequence: temporary shoring installed first, cuts made with cold methods and spark containment, new built-up sections fitted and bolted before shoring released. Total-station readings were taken before, during and after each cut against the 5 mm limit, and fire watch plus hydrocarbon testing ran on every shift. Works were grouped by rack bay so only one bay was ever open.

The result

Five weeks: 22 members reinforced, the new line supported and tied in, all deflections inside 5 mm, zero service interruption to the six existing services, zero lost-time incidents across 4,300 safe man-hours at a peak crew of 16.

Scope delivered

  • Staged modification design & load check
  • Temporary shoring installed first
  • Cold cutting with spark containment
  • Built-up reinforcement sections fitted
  • Deflection monitoring (5 mm limit)
  • Tie-in support for the new 20-inch line
Related service: Mechanical Works
SAFETY ON THIS PROJECT
0Lost-time injuries
4,300Safe man-hours
16Crew on site at peak
30Toolbox talks held
Six live services stayed running while they cut the rack apart around them. Deflection data on every bay, every day.
Piping engineer · Nawah Energy Services